Eugene, OR
Project Type: College
This project was a new construction and complete mechanical for Oregon Cascade. Once we were awarded the project and construction commenced, the job documents were barely 80% complete. And once work began, we had to adhere to a strict schedule and meet a firm end date so the basketball programs could start their PAC-12 seasons in early January. This required aggressive upfront coordination, during which 3D BIM was utilized, spearheaded in-house by Oregon Cascade. In some cases, we were installing pipe in areas where shop drawings had not yet been signed off on. This was accomplished by building a strong relationship with the design team and scheduling video conference calls and coordination meetings at least once and somethimes twice a week. This teamwork was a huge reason why we were able to pull it off and complete the project successfully.