Tigard, OR
Project Type: K-12 and Higher Education
This is a three phase project that Oregon Cascade started in 2017 and is scheduled to be completed in the summer of 2020. The initial phase consisted of the “investigation” phase that made this a design-assist project. Next there were two construction phases, with the first completed before the start of school in September of 2019. We are currently engaged in the final construction phase to be completed in time for the next school year to start. As part of the remodel, new heating water boilers took the place of the old steam boilers to heat the part of the building that stayed intact and were installed in time for the 2019 heating season. As with any construction that has to work around students and education schedules, it took a complex phasing plan to be able to complete the project.